Bridge Substructure Condition Assessment

South Brisbane

Overview

Condition assessment of reinforced concrete bridge substructure elements including piers, headstocks, and abutments. The bridge was approaching its 40-year design life and required assessment for life extension. Half-cell potential mapping identified active corrosion zones concentrated on the tidal splash zone of piers. Chloride profiling and durability modelling predicted remaining service life for each element, informing a prioritised maintenance programme.

Challenges

  • 01Access to substructure elements required under-bridge inspection units
  • 02Tidal zone access limited to specific tide windows
  • 03Testing programme needed to cover 24 pier elements across 6 spans
  • 04Results required for asset management budget submission within 8 weeks

Outcomes

  • 01Remaining service life estimated at 15 to 25 years for most elements
  • 024 pier elements required priority cathodic protection within 2 years
  • 03Provided 20-year maintenance cost forecast for asset planning
  • 04Enabled life extension decision avoiding early replacement at $40M+ saving